Friday, September 13, 2013

September Begins

September began with beautiful weather and the completion of the manure pit. Footings are being poured for the free stalls and the parlor.
Stripping the forms from the manure pit walls.









Inside the pit.

Loading dock poured and ready for materials being shipped.


Rebar, bent and tied, for reinforcement in the free stall and parlor footings.

Cutting rebar.

View from the new dairy site towards the manure pit.


Corner of the loading dock looking towards the upper free stall site.

Working and shaping the slope above the upper free stall.

Load of gravel delivered for the footings.

Footings in the first stage.

Digging the footings with framework standing by.






Footings

Completed footing form with pier support.






Beginning stages of footing with fabric placed and gravel on top.

Fabric placement in footing.