February was extremely rainy on the Big Island, so progress was slow but steady.
 |
Walls formed for the compost building. |
 |
Footings poured for the parlor. |
 |
With the footings poured, you can now see the "footprint" of the milking parlor. |
Things began changing quickly, the end of February, as erection crews arrived.
 |
Steel erection begins on the freestall building. |
 |
Curb poured by the Gomaco crew. |
 |
Walls of the parlor being poured with a concrete pumper. |
 |
Front of parlor....aftermath of rainstorm in the foreground. |
 |
Gomaco crew pouring curb. |
 |
Inside of parlor. |
 |
Completed commodity shed. |
 |
Milking parlor. |
 |
Milking parlor in the foreground with freestall in the back. |
 |
The three notches in the far side of the parlor are the lower part of the three windows in the upstairs, office area. |